568 330 318 Free initial consultation · reply within 15 minutes
Administrative law · Construction

Construction Supervision - a Chain Where One Missing Link Voids the Whole Order

Construction supervision is the administrative field where the sums are largest and the deadlines shortest: the fine is calculated per square metre and reaches hundreds of thousands of lari on a multi-storey building, a halted site burns the investor's money every day, and an executed demolition cannot be undone. In the same field the body's procedure is written most rigidly: inspection, report, remediation order with a deadline, and only then a sanction.

This page describes how a construction supervision case is run from both sides: the builder facing a fine, a stop order or demolition, and the neighbour harmed by someone else's construction while the supervisory body "does not see it". Obtaining a permit, contractual disputes with a developer and legalisation of an unauthorised structure belong to the real estate pages.

Updated · Practice area: Administrative law lawyer

The chain of acts

Five Supervisory Acts and What Must Precede Each

Each act is challenged separately, and each needs the previous stage to have been lawfully completed - so the lawyer checks the chain backwards from the end.

ActWhat the law requires before it is issued and where the defence lies
Inspection reportThe inspector's authority, a ground for the inspection (schedule, complaint, information), the participation of the builder or a representative, photographs, measurements. Defence: a "breach" recorded without measurement or photograph is the inspector's word; the builder's remarks are entered in the report on the spot.
Remediation orderA specific breach, a specific rule, a reasonable deadline for remediation. Defence: an order to "bring into conformity with the project" without specifics cannot be performed and voids the subsequent fine; the deadline must be technically realistic.
Fine orderExpiry of the remediation deadline and a recorded failure to comply, measurement of the area, the class of the breach. Defence: recalculating the area (the fine is per sq m), the classification of the breach (classes I to V at different rates), proof that the order was performed in time.
Stop-work orderA breach that makes continuation dangerous or irreversible; a separate reasoned order. Defence: proportionality - partial rather than total suspension; the suspensive effect of the complaint; damages for every day of suspension if the act is unlawful.
Demolition orderAll previous stages, impossibility of remediation, legalisation ruled out. Defence: a motion for suspension in court on the first day; proof that legalisation is possible; partial rather than full demolition; third-party rights in the property.
What the lawyer does

Challenging a Construction Fine or Demolition Order - the Stages

  1. Reconstructing the chain

    The lawyer requests the whole supervision file (under the public information procedure) and lays out the sequence of acts: inspection - order - deadline - inspection - fine - stop order - demolition. A missing link or one inconsistent by date (a fine before the remediation deadline expired, demolition without a fine) voids the whole chain that follows.

  2. Factual verification on site

    Independent measurement: how many square metres the deviation actually covers, on which floor, whether it affects the structure or only facades and partitions. The fine is calculated on area, and the body's measurement often records an entire floor as a "breach" when the deviation is one room. An expert's report is the main piece of evidence in the complaint here.

  3. Classifying the breach

    Construction offences are divided into classes and the fine rate depends on the class; the body often applies a higher class ("unauthorised construction" instead of "deviation from permit conditions"). Reclassification cuts the fine several times over, and the argument survives even an admission that the breach occurred.

  4. Securing suspension

    An administrative complaint against a demolition or stop order as a rule suspends the act; in court a separate motion for suspension is filed the same day with proof of irreversible harm. The lawyer puts this ahead of every other argument - an annulled order does not bring back a demolished structure.

  5. The complaint and parallel legalisation

    A complaint on procedural and factual lines; in parallel, where the deviation can be legalised, an application for a project amendment or legalisation to the architecture service. Legalisation granted removes the basis for demolition and is an argument for reducing the fine.

  6. Claiming damages for an unlawful stop

    If a stop or demolition order is declared unlawful, every day the site stood still - the contractor's idle time, the investor's penalties, increased costs - is recoverable from the state or the municipality. The lawyer starts a separate record of costs from the day of the stop.

The neighbour

From the Neighbour's Side - How to Challenge Someone Else's Permit and How to Force the Body to Inspect

A neighbour has two different routes, and confusing them is a typical mistake. The first is challenging the permit itself: a construction permit is an administrative act, and a person whose lawful interest it infringes may challenge it within one month of learning of it. The interest must be specific: breach of the daylight standard, sanitary distance to the boundary, the height regime of the zone, occupation of a shared yard or passage, a cultural heritage zone. "I do not want this built here" is not an interest. Annulment of the permit removes the legal basis of the construction, and this is the strongest but hardest route.

The second is applying to the supervisory body for an inspection: construction often exceeds the permit (an extra floor, a larger area, a changed layout), and the body is obliged to record this and respond. The application names the specific breach with photographs and carries proof of delivery; the body must answer within the period, and inaction is challenged in court. The lawyer uses this route alongside the first: an inspection report confirming the deviation is evidence in the permit dispute too.

The question of the deadline - "when did the neighbour learn of the permit" - is often itself the subject of the dispute. The body and the builder argue that the information board hung on the site months ago; the neighbour argues that there was no board or that it did not show the permit number. The lawyer fixes the date of knowledge in writing (a request for a copy of the permit under the public information procedure - and the date of the reply) and files the complaint within one month of that date.

Figures

What a Construction Supervision Case Rests On

Fine per square metre
A construction fine is calculated on the area and class of the breach, at a higher rate in Tbilisi and the large cities; on a multi-storey building the total reaches hundreds of thousands of lari. Checking the area and the class is the first way to reduce the fine.
Classes of breach
From class I (a minor deviation) to class V (unauthorised construction on a site of special importance); the class determines the rate and the strictness of the procedure. The body "raising" the class is a typical subject of complaint.
Remediation deadline
The deadline is set according to the nature of the breach and must be technically achievable; a fine before it expires is not permitted, and an order performed in time excludes a sanction. Recording performance in writing is the builder's responsibility.
One month to challenge
Every supervisory order is a separate act with its own one-month period; for a neighbour, the permit is challenged within one month of learning of it. Leaving one act unchallenged strengthens the basis for the next.
Suspensive effect
An administrative complaint as a rule suspends a stop or demolition order; in court only a motion does. In a demolition case, a late motion is equivalent to losing the case.
Limitation on fines
A fine for a construction offence must be imposed within the statutory period from discovery of the breach; old deviations the body "wakes up to" years later are often time-barred - although the rule works differently for a demolition demand.
Documents

What to Bring to a Construction Supervision Consultation

  • The construction permit and the approved project (architectural part, site plan, areas) - to assess the deviation.
  • Every supervisory act in sequence: inspection report, remediation order, fine, stop or demolition order - with dates of service.
  • Your responses and evidence that the order was performed: letters, photographs, works reports, with dates.
  • An independent measurement or expert report on the area and nature of the deviation, if you already have one.
  • For a neighbour: dated photographs and video of the construction, the title document for your property, a preliminary assessment of the daylight or distance breach.
  • Cost documents for the suspension period: contractor invoices, investor claims, increased prices - for the damages claim.
Typical cases

Three Construction Supervision Cases

A fine on a whole floor over one room

The supervision service fined a developer for deviation from the project on the area of the entire top floor. The lawyer: an independent measurement showed the deviation was 40 square metres (a covered terrace), and the rest of the floor matched the project; moreover, the remediation deadline had not expired until two days after the fine order. The fine was first cut by 85% on area, then annulled entirely on the procedural ground, and the body was ordered to start fresh proceedings.

A demolition the court suspended on day one

A municipality issued a demolition order for an extension to a private house and scheduled enforcement within a week. The lawyer filed a claim and a motion for suspension in court the same day, substantiating irreversible harm; suspension was granted the next day. The file contained no remediation order at all - the body had gone straight from inspection to demolition. The order was declared void and the extension was later legalised.

A neighbour's complaint that worked on both routes

A nine-storey building was going up next to a neighbour's yard under a permit that did not match the height regime of the zone, and the construction also exceeded the permit by two floors. The lawyer: a request for a copy of the permit (fixing the date of knowledge), a complaint against the permit within one month on height and daylight grounds, and in parallel a request to the supervision service for an inspection of the deviation. The inspection confirmed the deviation and halted the construction; the permit dispute ended in a settlement removing two floors and compensating the loss of daylight.

Questions About Construction Supervision

The inspector came, drew up a report, and two weeks later a fine arrived - with no remediation order. Is that lawful?

As a rule, no: the supervision procedure provides for a remediation order and a deadline after the inspection, and a fine is imposed only after failure to comply within that deadline. Exceptions exist for certain classes and dangerous breaches, but skipping the order in a typical case voids the fine. The lawyer looks first for the order and proof of its service in the file.

I paid the fine so that construction could continue. Can I still challenge it?

Payment does not forfeit the right to challenge if the one-month period has not yet expired - a paid fine is refunded when the act is annulled. After the period, only restoration of the deadline or a request to the body to review the act on its own initiative remains. So payment and complaint should happen at the same time when continuing construction requires payment.

We genuinely deviated from the project, but it can be legalised. Can they still demolish?

Demolition is a measure of last resort, permitted only where remediation or legalisation is impossible; where the deviation does not breach the zoning regulations or safety standards, a project amendment and legalisation rule out demolition. The lawyer files the legalisation application alongside the complaint, and legalisation granted makes the demolition order moot.

I have written to the body three times about my neighbour's construction and there is no reply. What can I do?

Inaction is itself challengeable: after the period (one month as a general rule) expires, a complaint to the superior body and then to court, seeking an order obliging the body to inspect and respond. In parallel, the Public Defender and, if you learned of the permit only recently, a challenge to the permit itself. Your three letters with proof of delivery are the main evidence in that case - keep them.

The building is already commissioned and the flats are sold. Can supervision still fine or demolish?

Commissioning confirms conformity with the permit conditions and materially complicates a later sanction; the limitation period on fines also applies. But changes made after commissioning (an extension, a conversion) are a new breach, and flat owners often become the subjects themselves. The lawyer checks whether the breach occurred before or after commissioning and who the real subject is - the developer, the owners' association or the flat owner.

Lawyers for Construction Supervision Cases

In a construction supervision case time is counted by the chain of acts and the enforcement date, not in weeks. Within 15 minutes the coordinator connects you with a lawyer who knows the practice of the supervision service and the municipalities and files a motion to suspend demolition the same day.

No published lawyers in this category yet

That does not mean we cannot help. Call us - we will match you with a specialist for a remote consultation or from a nearby city.

Call: 568 330 318

A Fine, a Stop Order, a Demolition Order - or a Neighbour's Construction Nobody Will Stop?

At a free consultation the lawyer reviews the chain of acts, tells you which link is missing, by how much the fine is inflated on area or class and on which day the motion for suspension must be filed. The coordinator's call comes 15 minutes later, not more.

Call: 568 330 318